Success Stories.

We Build The Future.


ELSEWEDY Electric PSP in a very short period of time, became one of the top EPC firms in the region, and became a trusted company for the MENA region governments, and African Governments; and eligible for their energy projects.

Last Decade ELSEWEDY Electric PSP’s Accomplishments:
Africa : ELSEWEDY Electric PSP finalized and finished more than 50 EPC projects, among a wide range of countries, in various fields
Asia : Due to the success of ELSEWEDY Electric PSP in Africa, we found the ground ready to start building our success story in Asia. With more than 6 EPC projects in different fields, from South-East Asia to the Middle East. ELSEWEDY Electric PSP started achieving success in a very short period of time, with a strong foot in the market.

Accomplishments

World Wide Projects
Projects In 9 different countries
Projects in Egypt
Mega Watt Delivered to different Countries

Attaqa & Mahmoudia Power Plants

In 2015, Egypt was facing a severe energy cutout. Thus, the government launched an emergency plan to overcome its energy problem. The emergency plan was to deliver power to the grid, in a very short period of time; through establishing new Power Plants on fast track basis. ELSEWEDY Electric PSP contributed to such an amazing cause, and took two Power Plants and their substations. ELSEWEDY struck the world records, and achieved success in the following:
Delivered the first fast track project, in Egypt
The usage of Air freight in this project
Delivered power to the grid in 159 days
Delivered Electricity for 620,000 Egyptian homes

Morning Dew
Morning Dew
Morning Dew
Morning Dew

Beni Suef 4800 MW Power Plant

Morning Dew
Morning Dew
Morning Dew
Morning Dew
Morning Dew
Morning Dew

ELSEWEDY Electric PSP in 2015, took one of Egypt’s Mega projects, Beni Suef 4800 MW power plant. The achievements achieved in Beni Suef are numerous.
In 150 days:
Installed 6 Main and 6 Main Auxiliary Transformers.
Installed 6 gas turbines including all auxiliaries
Erected 10,150,000 Kg of Steel structure
Poured 115,000 m3 of reinforced concrete
Demolished 1.75 Million m3 of Hard Rock
In 90 days:
Installed 6 Main and 6 Main Auxiliary Transformers.
Installed 6 gas turbines including all auxiliaries
Erected 10,150,000 Kg of Steel structure
Poured 115,000 m3 of reinforced concrete
Demolished 1.75 Million m3 of Hard Rock